Raise and Upgrade Berm

Location
Thompson Creek Metals - Endako Mine, Endako, BC

Project Description

The work consisted of:

  • Raising and upgrading the tailings berm by approximately 5 meters throughout the 50 hectare facility
  • Loading, hauling, placing and compacting 4000m3 material per day for a total volume of 350,000m3
  • Loading, hauling and placing shot rock required to construct and raise pump house, dam and weirs 5 meters in elevation (400 lineal meters) – total volume 45,000m3