Location
Village of Fraser Lake, BC
Project Description
The project involved the construction of a new sewage lagoon. The work included:
- Design, supply and install site environmental control measures
- Clear and grub approx. 2.5 Ha
- Excavate and haul waste off-site approx. 12,000m³
- Construct berms and import approx. 10,000m³ of borrowed material
- Supply and install approx. 300m of 25mm water service
- Supply and install approx. 171m of 50mm HDPE sanitary sewer force main
- Supply and place approx. 500m of perimeter fencing
- Hydro-seed approximately 3 Ha